GAO Says ICE Expanded Detention Without Updated Spending Plans or Full Cost Estimates

ICE headquarters in Washington, D.C., 2009 archive. Ser Amantio di Nicolao, CC BY3.0, cropped. Agency context, not a detention warehouse or current purchase.
URL has been copied successfully!

ICE headquarters, Washington, D.C., 2009 archive. Ser Amantio di Nicolao / Wikimedia Commons, CC BY 3.0; cropped. Agency context, not a detention warehouse or current purchase.

Federal auditors said Thursday that Immigration and Customs Enforcement expanded its detention facilities without keeping its spending plan up to date or fully assessing the cost of its investments, raising concerns about how the agency is managing billions of dollars in taxpayer funding.

The Government Accountability Office said ICE had not determined the scope, timing and estimated costs of further facility purchases. Its spending plan also failed to reflect a scaled-back warehouse initiative and other planned acquisitions, leaving an inflated estimate of planned obligations.

The Department of Homeland Security agreed with GAO’s two recommendations: update detention spending plans in line with ICE policy, and develop life-cycle cost estimates and evaluate alternatives before significant future facility investments. Both recommendations remain open.

Warehouse purchases outpaced planning

ICE received $45 billion for immigration detention in July 2025, with the money available through fiscal year 2029. That funding covered existing facilities as well as expansion. It is not an amount GAO said had all been spent.

The agency bought 11 warehouses for about $1.07 billion, then significantly reduced the initiative and planned to sell seven of them. In July and August 2026, it also bought four existing detention facilities for about $2.2 billion, according to the report.

GAO said ICE did not manage its detention-facility investments in accordance with DHS acquisition practices, which include estimating costs over a facility’s life cycle. Without those estimates before further purchases, the agency is less able to assess the investments and reduce potential waste.

The report concerns decisions and spending plans examined during the audit. It does not announce a new warehouse purchase on Thursday.

Oversight staff face a larger workload

Auditors said rapid expansion had increased the workload of staff who oversee facilities and validate invoices. ICE was working to fill 55 of 87 allocated positions nationwide for those duties.

Facility costs also varied. The median daily rate at the nine Federal Bureau of Prisons facilities used by ICE was $180 per detained person, compared with $151 at privately operated facilities. Rates at facilities used through agreements with the U.S. Marshals Service or state and local governments ranged from $85 to $103.

Those rates are not a like-for-like measure of efficiency. ICE officials told auditors that services, detention standards and location also affect what facilities charge.

GAO reviewed detention-expansion documents, spending plans and facility costs from October 2022 through various points in 2026, and interviewed headquarters and field officials. The findings focus on planning, investment analysis and oversight.

The report, GAO-27-108665, was published and publicly released November 19.

JBizNews Desk | Washington

Share this story:
Share on Facebook
Share by Email
X (Twitter)
Follow Me
Tweet
Whatsapp
LinkedIn
Copy link